Tuesday, August 4, 2009
Blower Door Test
As the project is completed, the home undergoes various tests including the blower door test. This procedure measures the amount of air infiltration (or exfiltration) by volume at a given pressure over a period of time. This data is fed into computer programs that help extrapolate the home's overall performance. This test is part of the LEED program's verification process whose purpose is to ensure energy saving measures have been successfully implemented.
Sunday, July 26, 2009
Landscaping
The landscaping package has been installed. Designed by landscape architect Janie Cantin, the plan takes into consideration native, drought tolerant plants and the local and regional climate as well as the micro-climates around the home. This creates sustainable landscaping that requires less irrigation and contributes to LEED points.
Friday, July 3, 2009
Driveway Installation
Mechanical, plumbing, and electrical trim outs are being finalized in the house. Meanwhile, the driveway is excavated and layers of gravel and sand have been compacted to accept the open grid pavers. Open pavers provide a way for water to penetrate what would normally be a solid impermeable surface. This allows more stormwater to infiltrate on site and also reduces the heat island effect, both contributing to LEED points.
Saturday, June 13, 2009
Begining Cabinetry Installation
Tuesday, June 9, 2009
Interior Paint
Monday, June 8, 2009
Tile Installation
Thursday, June 4, 2009
Wednesday, May 20, 2009
Monday, May 11, 2009
Spray-In Cellulose Insulation
Saturday, April 25, 2009
Mid-Construction Site Tour
Thursday, April 23, 2009
Spray Foam Insulation
A two part urethane foam has been sprayed at key locations to add thermal protection and to seal the envelope. The application has been made to the wood "band" in the crawl space and the "band" between the first and second floors. Also, the under side of the roof and all of the soffit areas have been sprayed to completely seal off all air leakage to the outside.
Tuesday, April 21, 2009
HVAC Rough In
A 16 SEER variable speed split system elecrtic heat pump has been installed. This is a high efficiency system whose controls monitor outside air temperature and bring in free heating or cooling when possible. The mechanical ventilation is also necessary to bring fresh air into the ultra-tight building envelope.
Friday, April 17, 2009
Electrical Rough In
The 200 amp electrical system has been installed and all circuits wired. We have also installed conduit that links the attic space to the crawl space and then to the main electrical panel. This will allow photovoltaic cells and/or solar hot water systems to be installed on the roof at a later date with little disruption. The house is in essence "solar ready" and can accept technologies that may become more affordable in the future.
Thursday, April 9, 2009
Plumbing Rough In
Tuesday, April 7, 2009
Friday, April 3, 2009
Windows, Doors, Roof and Siding
The roof, windows, and doors have been installed and the siding is going up. The roof color is as light as possible to reduce the home's heat island effect. The windows and doors incorporate Low-E glass and argon gas to increase envelope performance. The detail picture shows flexible DuPont flashing membrane installed to avoid seaming at corners.
Monday, March 30, 2009
Friday, March 20, 2009
Second Floor Sheathing
Framing/Insulation Efficiencies
First Floor Framing
Wednesday, March 18, 2009
Foundation Envelope Sealing
Tuesday, March 17, 2009
Foundation Framing
Thursday, March 12, 2009
Foundation Waterproofing
Foundation Insulation
Tuesday, March 10, 2009
Utility Excavation
Continuous CMU Foundation
Sunday, March 8, 2009
Footing Excavation
Existing Site
Building Permit
Saturday, March 7, 2009
Project Design
Subscribe to:
Posts (Atom)